Wednesday, February 12, 2014

House (Almost) Done

We have been battling the polar vortex the past few months with record setting temperatures in the single digits and snow and ice and you name it.  Therefore, we are still not in our house.  We should have been moving in the end of January but here it is, mid-February and still not in.  At the beginning of the building process last summer, it rained 6 straight weeks and now here at the end, snow and ice.  We really picked, weather-wise, a bad time to build but at the end of it all, its definitely going to be worth it.  I subbed out all of the work myself, even did some of it on my own.  Here are a few of the roadblocks we have battled throughout the process:
-6 straight weeks of rain
-concrete guy pouring my footers wrong (had to cantilever my framing)
-had to cut out framing after it was done to run pipe for gas logs
-roofers flashed incorrectly around chimney and windows not caulked so had flooded master bedroom and family room
-had flooded crawl space due to brick guys not building up crawl space opening (rain would run down side of my house and into crawl space) - bought sump pump to pump out water on a consistent basis until crawl space opening was built up 8 inches - spent many days under there moving dirt around to limit the amount of water build up and to level it out (back took a hurtin' on those days)
-tankless water heater pipes busted due to extreme cold weather, flooded crawl space even more
-determined there was a natural spring on the left side of my lot where the driveway was going - landscaper had to put in a drainage system to send the water out the back of the lot
-grader busted main water line going to the house, water was spewing everywhere (plumber fixed same day so not that big of an issue)
-tried to get painters to the house for 3 weeks, they never showed - had to go with different painter who was more expensive but he was really good and accommodating
-tried to get garage poured for 2 weeks, they never showed - called different company, they were out there in less than 2 hours to pour it for me
-pushed back 2 weeks on getting driveway poured due to freezing temperatures
-tile ordered wrong, had to re-order (took over 2 months from start to finish to get tile work complete)
-double oven cabinet ordered wrong, had to modify cabinet to lower double oven
-one of the three French doors leading to back porch was sent from the manufacturer with a faulty locking mechanism (took over 2 months to get fixed)
-3 times, my heat stopped working; 3rd trip to fix it was a charm; have not had any problems since
-our white Carrera marble top for the master bath was installed with a seam in it - we had told to the fabricator we wanted a solid piece - we waited a month and a half to get it replaced

I'm sure there are some obstacles I missed but these were the main ones I can remember.  Overall, being the builder and homeowner definitely increased my stress level but I keep reminding myself that it will be worth it once complete.  Being the first house I've built from start to finish, I learned a lot.  There are so many things I didn't realize that goes into building a house, so many decisions that have to be made spur of the moment in order to keep production moving.

The #1 issue I encountered was subcontractors not showing up, not calling back, not completing their work in a timely manner.  However, here are a few of the good ones:
-cabinet specialist and the installers were always on time, very knowledgeable and did everything I asked of them
-electrician was efficient and extremely respectable
-plumbers always came out same day when asked (which was a lot)
-hardwood flooring installers finished in one day with no issues (and there is quite a bit of flooring, they didn't speak English but luckily, they didn't have any questions for me)
-framers (whom I knew from previous work) were great and had fun while working (every time I would go out there to check on them, they had their latino music playing and singing; it was a lot of fun to be out there with them)
-painters did everything I asked, they worked after hours when needed

Again, it was a great experience and I learned so much.  After 7 months of construction, we can't wait to move in next week and get settled in our home.  Below are a few random pics of the process.  I will do another blog once fully completed with more pics of the finished product.